1. Project Information
Project:Baltimore City Emergency Snow Removal
Division:Poly Division – M&T Integration
Location:Poly Site and M&T Stadium – Baltimore, Maryland
Client:City of Baltimore
Prime Contractor:James W. Turner Construction, Ltd. (JWTC)
Mobilization Date:February 1, 2026
Operational Transition Date:February 5, 2026
2. Operational Summary

The Poly Division was mobilized on February 1, 2026 in support of Baltimore City's Emergency Snow Removal operations. The Poly Division operated independently from its designated site from February 1 through February 5, 2026, conducting snow removal and hauling operations in accordance with City directives.

On February 5, 2026, the Poly Division was transitioned and consolidated into the M&T Stadium operation. This consolidation was implemented to improve logistics, enhance traffic flow, and increase overall operational efficiency. All Poly Division equipment was redeployed to M&T Stadium, and Poly Division crew managers were integrated into the unified M&T Stadium command structure.

Following the transition, Poly Division personnel and equipment continued operations at M&T Stadium through final demobilization. All work was performed in accordance with the scope of work and City directives.

3. Equipment Deployment

All equipment initially assigned to the Poly Division was redeployed to M&T Stadium on February 5, 2026 as part of the operational consolidation. Equipment was incorporated into the M&T Stadium peak allocation. Refer to the M&T Stadium Close-Out Document for consolidated equipment figures.

4. Operations Management / Supervisors
RoleNameShiftPhone
Lead Operations Management
Lead Operations ManagerPatrick Haygood903-578-1713
Secondary Operations ManagerScott Bryan252-571-7261
Poly Division Crew Managers
Crew ManagerDaniel HonakerDay Shift513-687-3103
Crew ManagerNick GrangerSplit Shift518-932-1898
Crew ManagerCristian DelanoNight Shift512-734-1851
5. Completion Statement
6. Punch List

All identified punch list items have been completed. Should the City wish to add additional punch list items not reflected herein, such items must be submitted in writing.

7. Release / Acceptance

By signing below, both parties acknowledge that the work described in this Close-Out Document has been completed in accordance with the project requirements. This document serves as formal notification of project completion and request for acceptance.

JWTC Representative
Signature
 
Printed Name
 
Title
 
Date
City of Baltimore Representative
Signature
 
Printed Name
 
Title
 
Date
8. Photo Documentation

Photo documentation for the Poly Division is included within the M&T Stadium Close-Out Document, as operations were consolidated. Refer to M&T Stadium Photo Documentation for relevant imagery.